Flagstone 2 storey cottage Refurb and extensions
A complete renovation of the existing cottage, removal of the roof, walls to FF, rear wall to the GF, underpinning external walls, and footings where required.
Adding two substantial 2 storey extensions to the rear and side of the cottage, mixing old with new, using 172mm SIPs linked with a glazed 2 storey link with pitched roof. Double garage and plant room.
Groundworks completed, piling, underpinning, slab and upstand. Now onto the SIPs, 2 weeks on site, having taken delivery of complete SIPs package, top hung metal web joists (for ease of running services) Steels, Glulams, TF internals & P5 decking, finishing off the snagging to move onto the FF. Crane due this week to lift on the FF SIPs panels, Steels & TF internals. 5 Weeks and the SIPs is all installed, now final nailing, gluing, foaming before the breather membrane goes on and then the batten, ready to received PV, guttering and roofing. Slate roofing and Lead work, looking great. Solar panels fitted & Electricians and plumbers now started internally.